Draw the activity-on-node (AON) project network associated with the following activities for Dave Carhart's consulting company project

Production and Operations Management



MGT 455 Module 2: Assignments



Module 2: Topic and Objectives

Project Management



Module 2: Assignments



Problem 3.3 Draw the activity-on-node (AON) project network associated with the following activities for Dave Carhart’s consulting company project. How long should it take Dave and his team to complete this project? What are the critical path activities?



Activity Immediate Predecessor Days

A - 3

B A 4

C A 6

D B 6

E B 4

F C 4

G D 6

H E,F 8



Click here for the SOLUTION