The following data reflect the current month’s activity for Sills, Inc

ACCOUNTING

Variable cost variances

The following data reflect the current month’s activity for Sills, Inc.:

Actual total direct labor …………………………………………………………. $546,000
Actual hours worked ……………………………………………………………… 26,000
Standard labor-hours allowed for actual output (flexible budget)…. 27,000
Direct labor price variance ……………………………………………………. $ 19,500 U
Actual variable overhead …………………………………………………………. $132,000
Standard variable overhead rate per standard direct labor-hour ……. $ 5.25

Variable overhead is applied based on standard direct labor-hours allowed.

Required:
Compute the labor and variable overhead price and efficiency variances.